BOM revisions, part drawing history and frozen BOMs
Example. The customer asks for a heavier frame on a standard conveyor. Engineering revises the conveyor's item master and it is approved. The conveyor's BOM now warns that its item master has been revised. The designer clicks Revise BOM, changes the frame line, enters the reason Heavier frame, customer request and clicks Submit Revision. Version 2 becomes active and version 1 is kept as Revised.
There are three ways a BOM changes over time:
| Change | Use | Result |
|---|---|---|
| The product itself changed | Revise BOM | A new BOM version; the old one becomes Revised |
| One part's drawing changed | An ECN | A new drawing revision on that line; same BOM (Engineering change notes) |
| Production started on a work order product | — | The BOM that work order uses is Frozen and can't be edited |
When a BOM needs revising#
Approving a revised item master flags the BOMs that use it:
- The BOM's own product was revised: the BOM shows ⚠ This BOM Item Master has been revised, Please revise the BOM before proceeding. and the BOM view offers Revise BOM.
- A part on the BOM was revised: the BOM shows ⚠ The following items in this BOM have been revised; Please check before proceeding. with each old item code, its new code and revision number. A part with its own child BOM has → Revise BOM, which opens that child BOM. Custom BOMs don't show this list. Revised lines are highlighted (Item Revised).
A BOM flagged only because of a revised part has no Revise BOM button of its own: revise its product first if the BOM itself must change.
Before you start#
✅ Before you start
0/3 readyRevise a BOM#
Open the BOM
📍 Production → Bill Of Materials → ViewClick Revise BOM at the top right.
Make the changes
📍 Revise Bill of MaterialThe window warns This will create a new revised BOM entry. No approval required please verify and submit. The Finished Product* is locked. Change Validity, Drawing No, Department, Designed By and the lines (Edit BOM, then Save BOM). Enter the Reason/Remarks*.
Submit
📍 Submit RevisionSubmit Revision stays greyed out until something has changed. After submitting, the window closes with BOM has been revised successfully! and you stay on the old version, now Revised. Go back to Production → Bill Of Materials to open the new Active version.
What revising does.
- The old BOM becomes Revised and inactive; its view says This BOM has been revised. The next version will be v….
- The new BOM gets the next Version No, status Active, the product's latest item master revision, and says This BOM has been revised from v…. The person who submitted the revision is its creator, so only they can edit or cancel it from the screens.
- BOMs that used the old one as a child now point to the new version, and the parent's line takes the part's latest item code. Child BOMs of the old version move to the new version.
- A new BOM PDF is made and both changes are recorded in the Audit Log.
- There is no approval step.
A part's drawing revision history#
When an ECN is completed for a line, that line's ECN column shows the ECN number and View History. View History appears only after the line's first completed ECN. It opens Revision History — part with Date, Changed By, Old Rev No, New Rev No, ECN No, Old Files and New Files. Click the ECN number to open the ECN.
Frozen BOMs#
A BOM is frozen automatically when production starts for the work order product that uses it: when its job cards are created (processing starts), at the first material issue for that product, or when its finished goods are received, whichever comes first.
- A BOM made for that work order is frozen itself.
- A product that still uses its shared BOM (Standard products) doesn't freeze the shared BOM. The work order gets its own frozen copy, numbered BOM-work order number-NNNN, and the product uses that copy from then on. The shared BOM stays editable for new work orders. The Audit Log of the copy records which shared BOM it was made from.
On screen:
- the BOM list shows the number in blue and Edit is greyed out with Frozen can't be edited;
- Update BOM on the work order is greyed out (Process already started for this product);
- Cancel is greyed out with Bill Of Material is frozen and cannot be cancelled.
There is no unfreeze. To change a frozen BOM, raise an ECN for a part drawing, or revise the product and then the BOM.
Statuses: Active, Revised, Frozen, Cancelled.
Rules to know#
- Revise BOM appears only when the BOM's own product has a revised item master, and the BOM isn't cancelled or already revised.
- The Reason/Remarks is required.
- A revised BOM can't be edited or cancelled.