Record production completion and receive finished goods
Example. Four conveyors on work order 0042 have passed final inspection. The quality engineer, who has the product assigned in the Quality department, opens Products → Show More → Mark Completed, enters Completed Qty 4, chooses the Finished Goods store and the dispatch in-charge, enters the four serial numbers and clicks Mark Complete. The conveyors are now in stock, the product moves to the Dispatch department and the customer order line is ready for dispatch.
What it does. Mark Completed records how many units of a work order product are finished and receives them into a store as a production receipt. It is the moment finished goods enter stock; completing job cards doesn't. The work order must belong to the Company and Location you are working in.
When to use it#
After the product's job cards are done and, usually, after final inspection. You can record part of the quantity now and the rest later.
Before you start#
✅ Before you start
0/8 readyStep by step#
Open Mark Completed
📍 Work order → Products → product's Show More → Mark CompletedThe window This product will be added to inventory under Finished Goods. Do you want to proceed? shows Sr No, Product, Ordered Qty, Pending Qty, Completed Qty, Store and Assign To. If a job card of the product is still open, the window says Complete or cancel job card … before marking this product completed. with the job card numbers, and Mark Complete stays greyed out.
Enter the details
📍 Mark Completed window- Completed Qty: units finished now. The field can't go above the pending quantity, and Mark Complete stays greyed out at zero.
- Store (required): Select Production Receipt Store. Only active stores at the work order's Location that can receive production or hold finished goods are listed; the store marked as the default production receipt store is chosen for you.
- Assign To: Select Department Incharge, the person who takes the product next (usually dispatch).
Serial numbers (serial-tracked products)
📍 Serial NoChecking the current item master for serial tracking. appears first. For serial-tracked products enter one serial per unit in the Serial No rows (you can paste several from Excel into a row); a problem with a serial is shown under its row. Enter a whole completed quantity to add one serial number per unit. appears until a whole quantity is entered.
Confirm
📍 Mark CompleteMark Complete (Processing...) stays greyed out until the quantity is above zero and within the ordered quantity, no job card of the product is open, and the serial check is ready. On success Product marked complete successfully appears.
What happens#
- Inventory: the quantity is received into the chosen store as a production receipt (a stock movement against the work order). Only Manufacturing products add stock; Service and Bought Out products don't. Serial numbers you entered are registered for the receipt.
- Value of the receipt: the work-in-progress value of the product is the material issued to the work order for it, less material returned and less the value of finished goods already received. Each receipt takes its share of that value by quantity; the receipt that completes the product takes all that is left. When no material was issued, the receipt is valued at zero.
- Finance: no accounting journal is posted for the production receipt at present (the same applies to material issues and returns); the value is kept on the stock movement.
- BOM: the work order's BOM is locked. A Standard product that still uses the shared master BOM gets its own frozen copy for this work order.
- When the full quantity is completed: the product moves to the Dispatch department of your Company and Location (created if there is none), the person you chose in Assign To is recorded in the product's history, its open tasks are completed, and the menu item reads Marked As Complete.
- Sales: the customer order line becomes Ready For Dispatch (with Finance on), otherwise Partially Closed or Closed.
- Work order: it becomes Completed when every product is complete, and the linked customer order, quotations and inquiry get a timeline entry saying so.
- Next: dispatch on a delivery challan (Delivery challans).
Final inspection from the work order#
Show More → Final Inspection starts a final inspection for the product. It is offered to the product's Quality assignee. See In-process and final inspection.
Why Mark Completed is greyed out or refused#
| Message | Reason |
|---|---|
| Complete or cancel job card … before marking this product completed. | A job card of the product is still open (shown in the window, and refused if the receipt is attempted) |
| Cannot mark product as complete due to unresolved FAT remarks. | A FAT remark for the product is still Pending |
| Cannot mark product as complete due to a quality issue. Please resolve the issue. | The product has an open quality issue |
| Cannot complete …: it has no product type on Work Order …, so no Finished Goods would be posted. Set the product type (Manufacturing for goods made here) on the Work Order, then complete it. (error message after Mark Complete) | The work order product has no product type; nothing is saved |
| This product has already been marked as completed. | The full quantity is already received |
| (greyed out, no message) | The work order is cancelled, amended or completed |
| Serial tracking could not be confirmed from the current item master. Receipt is blocked. | The item master couldn't be checked; try again |
| Registered serial numbers could not be checked. Receipt is blocked. | The serial check failed; try again |
| (Store field marked Required) | No store chosen; pick a Production Receipt Store |
| You do not have access to the selected store. (error message after Mark Complete) | Your user has no access to the chosen store; ask your administrator to give you access, or choose another store |
| Cannot record production of … for Work Order …: raw materials have not been issued to this Work Order (…). Issue the materials through Material Requisition and Material Issue before completing production. (error message after Mark Complete) | The Company requires material issue first, and some material is short of what the BOM needs; the message lists each item's required, issued and short quantity |
| Cannot record production of … for Work Order …: its BOM has material requirements but no raw materials are planned on the Work Order. Start production processing and issue the materials before completing production. (error message after Mark Complete) | The Company requires material issue first and the product was never started, so no raw materials are planned |
| Finished goods already received for this Work Order exceed the value of materials issued to it. Ask Finance to review Work Order WIP costing before recording more production. (error message after Mark Complete) | The value already received as finished goods is more than the value of material issued to the work order |
The material-issue setting#
Admin → Application Settings → Production → Work Order Completion → Require Material Issue Before Work Order Completion is set for the Company you are working in and saved as soon as you switch it (you need App Settings update permission). When it is on, finished goods can be received only after the required raw materials have been issued to the work order. When it is off, you can complete without a material issue. Issue material through Material for production; when goods bought for the work order on a purchase request are added to inventory, Request Material on the GRN opens a material requisition for them, which is then issued with a material issue note (Manage GRNs).
Rules to know#
- Mark Completed is shown only to the product's assignee in a Quality-type department.
- A product can't be received while any of its job cards is open.
- The completed quantity can't exceed what is still pending.
- Serial-tracked products need one unique serial per unit.
- A work order can't be set to Completed by hand; it completes when production is recorded for every product.