Production planning and delay tracking

ProductionUpdated 25 Nov 2026

Example. A work order for 4 conveyor frames is dated 3 March. The planner opens the work order's Production Planning tab and creates a plan for the frame: Design 2 days, Fabrication 5 days, Painting 1 day, Quality 1 day, Dispatch 1 day. In the same window she picks the purchase planning template Steel and paint with a purchase target date of 6 March. The target dates skip Sundays and holidays. When the frame moves from Fabrication to Painting two days late, the Fabrication stage gets its actual date, and the predicted completion moves out two days. The painting supervisor, responsible for the next stage, sees the yellow delay banner and opens Delayed Production Plans.

Before you start#

✅ Before you start

0/5 ready

Plan a product#

  1. Optional: keep a template

    📍 Production → Production Planning → Planning Templates → Create Template

    A template is a reusable list of stages: Template Name (unique), Description and, under Department Planning, the stages in order with a Stage Name, Department and Responsible Person (filled in from the department's in-charge). Drag rows to reorder. Templates hold no days; you enter those on each plan. See Production setup.

  2. Create the plan

    📍 Work order → More → Production Planning → product → Show More → Create

    Only products of type Manufacturing are listed. Create opens Create Production Plan and Purchase Plan with the work order and product. Choose a Template, or Copy From another product of this work order that already has a plan. For each stage enter the Department, Responsible Person and Target Days (at least 1). Calculated Target Date fills in: stage 1 counts from the work order date, each later stage from the one before, counting only working days.

    Under Purchase Planning, choose the Purchase Planning Template and the Purchase Target Date (both required), and optionally the Delay Intimation Users. Confirm stays greyed out until both are filled in. Click Confirm: the production plan and the purchase plan are created together, and if either one is refused, neither is kept.

    The last stage's date becomes the product's target, and the work order's Our Target Date and Predicted Completion Date are worked out again. A product can have one active plan. If the product is already in one of the plan's departments, that stage starts straight away.

  3. Let the stages move

    📍 Work order → Products → Start / Update department, or Bulk Update

    There is no button to complete a stage. When you move the product to the next department, the old department's stage is Completed with today as its actual date, and the new department's stage becomes In Progress. The predicted completion date is recalculated: finished stages use their actual dates, the rest are projected from today. The old department's tasks are completed. When every stage has an actual date, the plan is Completed.

    Stages are matched by department, not by order. If the product moves to a department that isn't in the plan, the old stage is completed but no new stage starts.

  4. Change the plan if needed

    📍 Production Planning tab → Show More → Update

    Update is available only to the plan's creator whose role has Production Planning update; for anyone else it is greyed out with You don't have permission to update production plan. Once the plan is completed it is greyed out with Production plan is completed and cannot be updated. Change departments, people or days, add or remove stages, and give a Reason For Update. Stages already in progress or completed are locked, and a completed stage can't be removed.

  5. Warn about a delay

    📍 Production Planning tab → Show More → Warn Delay

    Only the responsible person of the current stage sees Warn Delay, and their role also needs Production Planning update, or the warning is refused. On a completed plan it is greyed out (Production plan is completed cannot warn delay). Enter Delay By No Of Days (at least 1) and Reason For Delay. The dialog shows the stage's planned date and the new predicted completion date. Confirming records the delay on the work order's remarks and moves the predicted completion date out.

    In this version no notification is sent, despite what the dialog says. And the next morning's recalculation clears a warning for a stage that is still within its target date. Tell the people affected yourself.

  6. Cancel a plan

    📍 Production Planning tab → Show More → Cancel

    Cancel is available only to the plan's creator whose role has Production Planning Cancel; for others it is greyed out (You don't have permission to cancel this entry or Only the creator or designated users can cancel this entry). Give the Reason For Cancellation* and click Proceed. A plan can be cancelled only before any stage has started (otherwise Cancel is greyed out with Production is in progress cannot cancel). The work order's dates are recalculated, and you can create a new plan for the product.

  7. Look after the purchase plan

    📍 Production Planning tab → Purchase Target

    The Purchase Target column shows each product's purchase target date and template, or Not created. Under it, Purchase history lists the changes; Update purchase target (Purchase Plans update) changes the Purchase Target Date and Delay Intimation Users, with a Reason for target date change when the date moves; Cancel purchase plan (Purchase Plans Cancel) asks for a Cancel reason. A cancelled purchase plan shows Purchase cancelled. Each change and the cancellation is listed under Purchase history and added to the work order's remarks. Cancelling the production plan or the work order doesn't cancel the purchase plan. How purchase plans are followed up is explained in Plan purchases and Purchase planning templates and work order purchase plans.

Statuses. Plan: Active, In Progress, Completed, Cancelled. The Production Planning tab shows Active (also for a plan in progress), Completed, or Not Created for products without a plan or whose plan was cancelled. Stage: Pending, In Progress, Completed, Cancelled.

Follow delays#

WhereWhat it shows
Delay banner (every page)You have N delayed Work Order(s) in production. Click here to review, for people responsible for a stage of a late plan
Delayed Production Plans (from the banner)Plans where a stage up to yours is past its target date or was warned. Columns include the target, actual and predicted dates, Delay Reason and Delay: Delayed By N Day(s) (red, the product's target date has passed), Will be Delayed By N Day(s) (orange), N Day(s) Ahead (green) or On Track
View Production Plan (Production Planning tab)Every stage of the work order's plans with its target and actual date, status and remark
Production Planning Summary (Production dashboard)Open Full View opens Department Delay Summary: each stage's department, responsible person, target and actual dates, Delayed By (which also counts days forecast with Warn Delay), and the original and predicted completion dates. The full view shows what the dashboard card loaded; if it keeps loading, go back and open it again with Open Full View once the card has loaded. Needs Production → Production Dashboard read. See Production dashboard

Every morning at 8:30 (not Sundays), the system looks at every plan. A stage past its target date without an actual date is marked late, with the reason Production delay detected by the system, and the predicted completion date is moved out. Nobody is sent a reminder: the delays show up in the banner and on the pages above.

  • The check covers every plan that isn't cancelled, in every active account. The time is the server's clock.
  • The new predicted completion date is always the plan's original completion target plus the number of days its most overdue stage is late. When no stage is late, it goes back to the original completion date.
  • This replaces any predicted date set the day before, including one moved by Warn Delay or recalculated from stage progress. A stage that isn't late also loses its delay days and delay reason.

Every Monday at 10:00, the people chosen in Application Settings → Production → Dispatch Notification Receivers get the task [Action Needed] Review Weekly Planned Dispatches, due at the end of the week (with the Tasks module on). Each Company's own setting is used. Each person gets one task for every Location of that Company they have access to; someone with no Location of that Company gets none.

Daily production report#

Production → Export Daily Reports asks for a Date (today or earlier) and, for administrators and people who can see everyone's production entries, the Member Names. It downloads Daily Production Report as Excel for your current Company and Location, titled with the Company's name: purchase requests raised that day for work orders or of type Others, job cards created, process stages completed, and new, in-process and completed work order tasks. It needs Work Orders Export.

Use it for the daily production meeting or to send a day's activity to management. An empty section means nothing of that kind happened on that day for the chosen members (for example, no purchase request was raised for a work order). If Export Daily Reports gives an error, check that your role has Production → Work Orders → Export and that the date isn't in the future.

Rules to know#

  • A production plan becomes Completed when every stage has its actual dates filled in.
  • When you record a delay on a plan stage, the number of delay days must be more than zero.
  • Each active planning template needs a name not already used by another active template of the same Company.

Common questions#