Engineering change notes (ECN): create, complete and cancel
Example. During fabrication of work order 0042, the bracket BRK-12 clashes with the motor. The production engineer raises an ECN: work order 0042, product Conveyor 6 m, part BRK-12, assigned to designer Rahul, reason Clash with motor mounting. Rahul gets a task, redraws the bracket, uploads BRK-12-R2.pdf under Upload New Drawing, ticks Production and Purchase as affected departments and submits. The bracket line on the BOM now shows revision BRK-12-R2.pdf, and the engineer gets a task to review the new drawing.
An ECN records a drawing change for one part of a work order's BOM and adds a new drawing revision to that part. Use it when one part changes; when the product itself changes, revise the BOM instead (BOM revisions and frozen BOMs). ECNs also work on frozen BOMs.
Before you start#
✅ Before you start
0/4 readyECN is under the Design menu, which appears when the Design module is switched on. ECNs belong to a Company and a Location: you see and raise the ECNs of your current Company and Location. ECN numbering and task settings are set for each Company under Admin → Application Settings → Design → ECN tab.
Create an ECN#
Open the form
📍 Design → ECN → Create ECNThe Enter Material Details card opens.
Choose what changes
📍 Enter Material Details- Customer Name (filled in from the work order's customer and locked once a work order is chosen);
- Work Order Number*, Product* (a product of that work order) and Part No* (a line of that product's BOM, shown as item code - description). The work order list offers the open work orders of your current Location (not cancelled, completed or amended) that you can see: all of them when Can View All Members Production Entries ? is set to Yes for you (Admin → Team → member → Production) or you have Is Admin on, otherwise those you created or are assigned to. When the product has no BOM on that work order, the form shows This product has no Bill of Materials on the selected work order, so there are no parts to revise.;
- Assign To* (the designer who will make the change; an active user with access to your current Location);
- Description and Reason For Change.
Create
📍 CreateThe ECN is Pending with the next ECN number of your current Company's ECN series. Its baseline is the part's current drawing. The assignee gets a task ECN (…) — Review design change for … when Tasks is on.
Find and read ECNs#
Design → ECN (Create ECN at the top) lists Date, ECN No, Customer Name, Work Order No, Product, Part No, Created By, Assign To, Status and Show More (View, and Edit while the ECN is neither completed nor cancelled). Filter by Status (Pending, Completed, Cancelled), Assign To, Created By and Date.
The ECN view has Details and Audit Logs. Details shows Date, ECN No, Customer, Work Order No., BOM No., Part, Assign To, Created By, Old Revision No, New Revision No, Description, Reason for change and Status, then the ECN's PDFs (once completed), Current Drawing and New Drawing. The work order and BOM numbers link to them.
Show More → Edit (the ECN's creator only — others see Only the creator or designated users can update this entry) opens Update ECN Details, where only the Description and Reason For Change can be changed.
Complete an ECN (assignee)#
Switch to Edit Mode
📍 ECN view → Edit ModeOnly the assignee sees the switch, while the ECN is neither completed nor cancelled.
Upload the new drawing
📍 Update ECN Details → Upload New DrawingUpload one PDF. Name it with the new revision: the file name (with .pdf) becomes the new revision number. Always upload the new drawing before Done: the screen doesn't insist on it, but completing without a file leaves the part with no drawing, and the revision is then numbered Rev 1, Rev 2 and so on.
Describe the effects
📍 Engineering change effects on follows, Affected DepartmentsWrite the effects and tick the Affected Departments: Raw Materials, Production, Quality, Sales and Marketing, Finance, Purchase, Design.
Submit
📍 Done → Mark ECN as Completed → SubmitDone stays greyed out until you change something in the form. Then: Once submitted, the ECN details cannot be changed again. Do you wish to mark this ECN as completed?
What completing does.
- The ECN becomes Completed, an ECN PDF is made (under PDFs, with the name, address and logo of the ECN's Company) and the assignee's ECN task is marked completed.
- On the BOM, the part's previous revisions become inactive, the new drawing replaces the part's files, and a revision entry is added with the old and new revision and files. The line's ECN column links to the ECN, and View History shows the history.
- The ECN's creator gets a task ECN (…) — Review updated drawing for … when Tasks is on.
Cancel an ECN#
On the ECN view click Cancel, enter the Reason For Cancellation* and Proceed. Cancel is greyed out for everyone except the ECN's creator, your role needs Cancel on Design → ECN, and on a completed ECN it is greyed out with This entry is marked as complete and cannot be cancelled. The assignee's ECN task is cancelled. Nothing on the BOM changes.
Rules to know#
- The Part No must be a part of the BOM of the product you chose, and that BOM must belong to your current Company.
- A cancelled ECN can't be completed, and an ECN is completed only once.