Quality issues and rejected items: resolve, review and decide

QualityUpdated 25 Nov 2026

Example. A final inspection finds burrs on two edges. The inspector raises a quality issue for the fabrication supervisor, who records the corrective action. The inspector reviews it and approves, and the issue becomes Resolved. Separately, 20 sheets failed incoming inspection: the inspector who recorded the rejection chooses Replacement with a due date and a responsible person, and the supplier's replacement arrives on a new GRN.

Quality issues#

  1. Raise the issue

    ๐Ÿ“ Quality โ†’ Quality Issues โ†’ Create Quality Issue, or from an inspection

    Choose the Date, the Quality Inspection it belongs to and the Part Number (required), and the work order and product. In the Issues Table, add each problem with Add Issue: its Category, the Responsible person (required) and a Target Date. Each responsible person gets a Review Quality Issue task, or a notification when the Tasks module is off.

  2. Resolve

    ๐Ÿ“ Quality issue โ†’ Resolve Issues

    The button appears only for a Responsible person who still has an unresolved row on the issue. Tick your rows, describe the resolution for each and click Submit Resolutions. The rows move to Awaiting Review, and the person who raised the issue gets a review task (with the Tasks module).

  3. Review

    ๐Ÿ“ Quality issue โ†’ Review Issues

    The button appears only for the person who raised the issue, while a resolution awaits review. They can't review a resolution they submitted themselves: submitting it shows You cannot review a resolution you submitted. Tick the rows, Approve or Reject each (a Remark is required to reject), then Submit Reviews. A rejection sends a Rework Required task to the responsible person (with the Tasks module), who resolves again.

The issue's overall status follows its issues: Open, then In Progress; Partially Resolved when every issue has been reviewed and some were approved and some rejected; Resolved when all are approved. It can also be Cancelled.

Before you raise quality issues#

โœ… Before you start

0/4 ready

The quality issue form#

FieldMeaning
Date*When the issue was found
Quality Inspection*The inspection it came from
Work Order, ProductFilled from the inspection where possible. Not shown for an incoming (GRN) inspection
Part Number*, Part DescriptionThe part with the problem. With a work order and product, Part Number lists the product's BOM parts; otherwise you type it
Issues tableOne row per problem: Issues, Category, Resolution, Target Date, Responsible, Files (Upload Files)

Category is one of: Design Deviation, Material Issues, Dimensional / Tolerance Errors, Visual / Aesthetic Defects, Functional Defects, Assembly / Integration Issues, Contamination / Foreign Matter, Packaging & Labeling Issues, Process Non-Conformance, Measurement / Calibration Errors, Handling / Storage Damage, Regulatory / Compliance Deviation, Documentation Errors, Environmental Exposure Issues, Human Error, Machine / Equipment Failure, Safety / Hazard Risk, Supply Chain / Vendor Issues, Late Detection / Missed Inspection, Customer Feedback / Complaint.

The number comes from the quality issue numbering. Each responsible person's task uses the Task Priority in the settings, and is due on the row's Target Date, or after the settings' due days when no Target Date is given.

Files and resolution history#

  • Upload Files in Resolve Issues attaches evidence to a resolution. Upload Files in Review Issues attaches files to a rejection.
  • The view shows Attempts for each issue. Open it for the Resolution History: Resolution Plan, Resolved By, Resolution Files, Approve / Reject Remark, Rejection Files, Reviewed By and Status. The Latest Resolution is marked.
  • Resolution files can be deleted only while that resolution is still pending review: "This entry has been reviewed and can't be deleted".
  • Files on the issue rows can be removed from the issue's Files column.

Cancel a quality issue#

Open the issue and click Cancel. The screen greys it out for anyone but the person who raised it (Only the creator or designated users can cancel this entry), and once it is Resolved ("Quality issues already resolved and cannot be cancelled"). Your role needs Cancel on Quality Issues. Enter the Reason For Cancellation and select Proceed. The issue becomes Cancelled, it can't be resolved or reviewed any more, and the open tasks of the responsible people are cancelled automatically.

Rejected items#

Rejected items come from incoming (GRN) inspection: the rejected quantity is listed under Quality โ†’ Rejected Items. There's no Create button. The rejected item belongs to the inspector who saved the incoming inspection: Edit is greyed out for anyone else (Only the creator or designated users can update this entry). Accept With Deviation has no such rule: anyone whose role has Rejected Items update can use it.

  1. Decide what to do

    ๐Ÿ“ Quality โ†’ Rejected Items โ†’ Edit

    Choose the Action Plan: Replacement, Return, Rework or Scrap. Replacement and Rework also need a Due Date and a Responsible Person, who gets a task (or, without the Tasks module, a notification) when you save. The action plan can't be changed once set.

  2. Or accept with deviation

    ๐Ÿ“ Rejected item โ†’ Accept With Deviation

    Give the Reason for Deviation and select Confirm. This overrides the rejection: the rejected quantity is added to the GRN line's and purchase order line's accepted quantity (and taken off their rejected quantity), and the rejected item becomes Resolved. It doesn't add the quantity to stock by itself.

    Accept With Deviation is disabled once a replacement GRN exists (This item has been replaced.), for a cancelled item (This item has been cancelled.), after acceptance (This item has been accepted with deviation.) and when your role has no Rejected Items update (You don't have permission to perform this action.).

  3. Receive the replacement

    ๐Ÿ“ Purchase โ†’ Goods Receipt Note

    A replacement arrives on a new GRN against the same purchase order and goes through incoming inspection again. See Purchase request to stock.

Choosing Return or Scrap records the decision only; arrange the return and any debit note separately.

Reminders for the responsible person#

The Responsible Person is reminded 7, 3 and 1 day before the Due Date and on the due date itself, at about 9:30 in the morning. There are no reminders on other days.

  • On a reminder day, if the person has no open reminder task for the item, a task such as Action required by 25-11-2026 for rejected item (โ€ฆ) is created. Its priority is High on the due date, Medium one day before and Normal otherwise.
  • If that reminder task is still open, the reminder is a notification that opens it instead.
  • The scheduled reminders need the Tasks module. Without it, the responsible person gets only the notification sent when someone else saves the item, and no reminders. Keep track of due dates in the Rejected Items register instead.
  • Reminders stop only when the rejected item is cancelled. A rejected item that is already resolved still gets them until its due date has passed, so the responsible person can ignore those.

Common mistakes#

Edit issues and rejected items#

  • Quality issue: Edit, greyed out for anyone but its creator and once the issue is resolved or cancelled. For each issue row that isn't resolved yet you can change the category, resolution, target date, responsible person and files (Upload Files in the Files column); resolved rows are shown read-only. With the Tasks module on, Notify Responsible Person About Changes or a new responsible person creates a new task for them.
  • Rejected item: Edit, greyed out for anyone but its creator (the inspector) and once the item is resolved or cancelled. Choose the Action Plan (Replacement, Return, Rework or Scrap; it can't be changed once set); for Replacement or Rework add the Due Date and Responsible Person, who gets a task.

Rules to know#

  • A cancelled quality issue can't be resolved or reviewed.
  • Quality Issues lists the issues you raised, those raised by members assigned to you and those where you are a Responsible person, or everyone's with Can View All Members Quality Entries ? (Admin โ†’ Team โ†’ member โ†’ Quality). Rejected Items lists the items you created, those of members assigned to you under Admin โ†’ Team โ†’ member โ†’ Purchase, and those assigned to you, or everyone's with Can View All Members Purchase Entries ?. Members marked Is Admin see everyone's in both lists. Both lists show only your current Company and Location.
  • Accept With Deviation is refused for a closed rejected item or one already accepted with deviation ("Rejected Item already processed.").
  • When a replacement GRN is inspected, the same rejected item is updated: it is Pending while nothing has been replaced, Partially Resolved while fewer than the rejected quantity have been replaced, and Resolved once they cover it.
Next step ยท QualityIn-process and final inspection โ†’