From purchase request to stock in your store
Someone in your team needs material. They raise a purchase request. Purchasing turns it into a purchase order for a vendor. When the goods arrive, stores records a goods receipt note (GRN). If the item needs checking, quality runs an incoming inspection. Finally, stores adds the accepted quantity to inventory, and only then does the stock appear in the store.
The process at a glance#
Before you order#
- Purchase agreements hold agreed item rates with a vendor. When agreement checks are on, purchase orders offer only the vendor's agreed items, at the agreed rate unless the agreement allows override; orders created from an RFQ aren't checked: see Purchase agreements.
- Purchase plans give a work order product a purchase target date when its production is planned: see Purchase planning.
Who does what#
A purchase request, status Open
Approve the request (if switched on)
Approval Approved, Partially Approved or Rejected
A purchase order, status Open; request lines marked as ordered
A GRN, Approved or Pending Inspection; no stock yet
Inspect the goods (if required)
Accepted and rejected quantities; a task (with Tasks) or a notification for the person who created the GRN
Stock in the chosen store, with batch and movement history
Process flow#
The process has two halves. The first ends with an order placed with the vendor:
Part 1: request and order
Swipe sideways to see the whole diagram, or tap Enlarge.
- Raise a purchase request.
- If approval is switched on, approvers approve or reject it. A rejected request is edited and goes back for approval.
- The purchase team creates a purchase order from the request lines.
- If purchase order approval is switched on, its approvers decide.
- The order is sent to the vendor.
The second half starts when goods arrive:
Part 2: receive, inspect, add to stock
Swipe sideways to see the whole diagram, or tap Enlarge.
- Goods arrive: stores creates a GRN against the purchase order. No stock yet.
- Lines marked Required Inspection go to quality; other lines can be added to inventory straight away.
- Quality records accepted and rejected quantities.
- Accepted quantity: stores adds it to inventory, which is the step that changes stock.
- Rejected quantity: a rejected item (replacement, return, rework, scrap, or accept with deviation). Replacements arrive on a new GRN.
How the documents connect#
What each document passes to the next
Swipe sideways to see the whole diagram, or tap Enlarge.
- The purchase request passes items and quantities to the purchase order.
- The purchase order passes vendor, price and tax to the GRN.
- The GRN passes lines that need inspection to the incoming inspection.
- The inspection passes accepted and rejected quantities back to the GRN and the purchase order.
- The GRN passes the accepted (or received) quantity, minus transit wastage, to the store.
Decision points and exceptions#
| Situation | What MSME Sales Booster does | What you do |
|---|---|---|
| The vendor sends more than ordered | The GRN refuses the extra quantity | Receive only the ordered quantity, or amend the purchase order first |
| The vendor sends part of the order | The order becomes Partially Delivered; the rest stays open for the next GRN | Create another GRN when the rest arrives |
| Inspection rejects some quantity | A rejected item is created, and the inspector who saved the inspection gets a task (when your company uses Tasks) | The inspector decides on replacement, return, rework or scrap; only that inspector, with Update on Quality → Rejected Items, can accept it with deviation |
| You are not ready to put goods away | Close the Add Items to Inventory window with Cancel | Use Add To Inventory on the GRN later |
| A GRN was entered wrongly | On the GRN, Edit and Cancel are greyed out for anyone other than its creator. Edit works until its items are in stock; Cancel while nothing is in stock and there is no inspection report or purchase invoice | Edit or cancel it (Manage GRNs); after stock is added, ask your stores manager |
| The vendor promises a later date | The order shows as delayed once its date has passed | Record it with Update Delivery Date (Track deliveries) |
| Stock already covers a requested line | The line is still open on the request | The request's purchase person closes it with Check Items Stock (Plan purchases) |
Approvals in your company#
Sample data used in these guides#
All examples use a fictitious company, Demo Industries Pvt Ltd, at the Location Pune Plant:
| Item | Detail |
|---|---|
| Item | RM-SS304-SHEET-2MM, "SS 304 sheet 2 mm", unit Nos, quality inspection required |
| Vendor | Sample Steels LLP |
| Store | Raw Material Store |
| Quantity and price | 100 Nos at ₹ 2,450 |