What you are doing

Recording exactly what physically arrived from the vendor, against the purchase order.

Why it matters

The GRN is the record of receipt: it updates what is still due on the order, sends lines for inspection, and is where stock is later added from.

Who
Stores / receiving
Where in the ERP
Purchase → Goods Receipt Note → Create New GRN
Already existsPurchase orderVendor invoice or challan
GRN
Leads toInspection task (if required)Add to inventory

Before you start#

✅ Before you start

0/3 ready

What to enter#

FieldRequiredWhat to putExample
Delivered DateYesWhen the goods arrived. Not a future date. If your company limits past dates (Block Past Dates Selection), an older date saves the GRN as Drafted until an approver approves it (see below)Today
VendorYesThe supplier; its open orders are listedSample Steels LLP
Purchase OrderYesThe order you are receiving against. An order that has approvers is listed only once it is Approved; rejected orders are never listedPO for the sheets
Your DepartmentAs neededThe receiving departmentStores
Vendor Inv No / Vendor Inv DateAs neededFrom the vendor's invoice or challanINV-4471
Is Replacement GRNShown only when the order has rejected itemsChoose Yes when this receives replacement goods for a rejected item—
Received QuantityPer lineWhat actually arrived100
Transit WastagePer line, only for items set up to record itQuantity damaged on the way (deducted when stock is added). The column appears only when an item on the GRN is set up for transit wastage in the item master0
Required InspectionPer line, when the Quality module is onTicked automatically when the item master asks for inspection; you can change itYes
Technical PersonWhen inspection is requiredWho will inspect the line: the list offers active members of your Quality department with access to this LocationQuality inspector
FilesOptionalPhotos, test certificates—

Steps#

  1. Start the GRN

    📍 Purchase → Goods Receipt Note → Create New GRN

    Choose the vendor, then the purchase order. If security recorded the arrival on a Gate Inward Note, open it (Purchase → Gate Inward Note) and create the GRN from there (see Gate Inward Note to GRN); the order, vendor and challan details are filled in.

    Create Goods Receipt Note form with Delivered Date, Vendor, Purchase Order, Your Department, Vendor Inv No and Vendor Inv Date, a Remarks table and the Items section
    1. 1Delivered Date
    2. 2Vendor
    3. 3Purchase Order
    4. 4Vendor Inv No and Vendor Inv Date
    The empty form, before anything is entered.
    Open the full-size screenshot of GRN: create
  2. Answer the replacement prompt, if shown

    📍 Rejected Items Detected

    If items from this order were rejected at inspection and marked for replacement, choosing the order shows Rejected Items Detected: Rejected items marked for replacement were found for the selected Purchase Order. Would you like to create a GRN for the replacement items? Click Yes, Create to receive the replacement goods (Is Replacement GRN is set to Yes and you choose the Rejection Item), or Cancel for an ordinary receipt.

  3. Choose the items

    📍 Items → Choose Items

    Click Choose Items. Select Inventory Items lists the order's lines with Item Code, Description, Ordered Quantity, Pending Quantity and Received Quantity (on a replacement GRN, the rejected items with Rejected Quantity instead of the ordered quantity). Tick the lines that arrived and click Add Items.

  4. Enter received quantities and inspection

    For each line, enter Received Quantity and, where the column is shown, Transit Wastage. Check Required Inspection, and choose the Technical Person who will inspect it. To set every line at once, use Set Inspection for All or Set Technical Person for All above the items and click Apply. Every line needs a received quantity above 0 (Please add at least one item to this GRN. Items must have a received quantity greater than 0.).

  5. Preview, then create

    📍 Preview GRN → Create

    Click Preview GRN to build the GRN document (your role needs GRN export), check it, then click Create. Create stays disabled until you preview (Please click 'Preview GRN' to enable the button), and changing anything after the preview means previewing again.

What happens after you create#

  • The GRN gets its number. Its status is Pending Inspection if any line needs inspection, otherwise Approved.
  • The purchase order's open quantities are updated.
  • When your company uses Tasks, each line needing inspection gives its Technical Person a task New GRN Inspection Requested (…) Against Item (…). Without Tasks, each Technical Person gets a notification instead.
  • The Add Items to Inventory window opens straight away (not for a Drafted GRN). For lines waiting for inspection, select Cancel to close it. You will add them after inspection.

GRNs with an old delivered date (Drafted)#

When your administrator sets Block Past Dates Selection (a number of working days; Sundays and the holidays of your Company and Location aren't counted) and Approvers for Blocked Dates in Admin → Application Settings → Purchase → GRN, the Delivered Date tooltip shows the allowed window. Choosing an older date shows GRN will be in Drafted status. On saving:

  • The GRN is saved as Drafted with approval Pending. Each approver gets a notification, and a task when your company uses Tasks. If you are one of the approvers yourself, it is approved straight away.
  • If no approver is set, the save is refused: GRN delivered date is older than the allowed … working day(s) and no approver is configured. Ask an admin to set Approvers for Blocked Dates in App Settings.
  • While it is Drafted, inspection tasks aren't sent, and the GRN can't be added to inventory (GRN is in Drafted status. Approve it before adding to inventory.) or invoiced (GRN is in Drafted status. Approve it before creating purchase invoice.). The purchase order's received quantities are already updated.
  • An approver opening the GRN sees Approval needed (This GRN has a delivered date outside the allowed past-date window and needs your approval.) with Approve (reason optional) and Reject (reason required). One approval is enough: the GRN becomes Pending Inspection (or Approved when no line needs inspection) and inspection tasks go out. After a rejection it stays Drafted until its delivered date is changed, which starts a new approval round. The Approvals tab shows the history.
  • Approving needs no GRN permission other than being one of the approvers (and GRN read to open it).

Transfer inspection tasks to someone else#

The Technical Person chosen on a line can hand their own uninspected lines to someone else, for example before going on leave. Only that original Technical Person sees the links: Update Assignee appears next to Inspect items (when the Quality module is on) for their lines that haven't been transferred yet, and Cancel Assignee appears once they have transferred lines. Nobody else, managers included, sees them.

  1. Open Transfer Inspection Tasks

    📍 Purchase → Goods Receipt Note → GRN → Update Assignee

    The table lists each line's Item Code, Description, Received Qty and Current Assignee. Lines already inspected can't be chosen.

  2. Choose the new inspectors

    📍 Transfer Inspection Tasks

    Tick the lines, and either pick one person under Bulk Assign To or choose a person per line under Transfer To. Enter the Transfer Remarks and click Transfer Tasks. When your company uses Tasks, the old inspection tasks are cancelled and the new person gets a task for each line.

  3. Undo a transfer

    📍 GRN → Cancel Assignee

    Cancel Reassigned Inspection Tasks lists the transferred lines. Tick them, give a reason and click Cancel Tasks: the transfer is undone. When your company uses Tasks, the transferred tasks are cancelled and the original Technical Person gets a new inspection task for each line, saying the task has been restored to them. Only lines that haven't been inspected yet are affected.

Both links need Quality → Incoming Inspection → Update in your role; otherwise Update Assignee shows You don't have permission to update assignee and Cancel Assignee shows You don't have permission to cancel Reassigned Inspection Tasks. Both are greyed out on a cancelled GRN, and Update Assignee also on a Drafted GRN (Cannot update assignee for drafted items). Transferring doesn't change the GRN's status.

Which GRNs an inspector sees. On Create Incoming Inspection, the GRN list offers only GRNs of your current Location that aren't cancelled and still have lines waiting for inspection by you. These are lines where you are the Technical Person, or lines transferred to you. Only those lines are shown. Once a line is transferred away from you, it leaves your list.

Preview, invoice and export#

  • Preview GRN on the create and update pages builds the GRN document from your template (it needs GRN export permission); saving needs it first. After saving, the PDF is created in the background and added to the GRN's Files tab.
  • Create Purchase Invoice on the GRN opens a purchase invoice filled in from it.
  • There is no Excel export of GRNs; GRN figures appear in the Purchase dashboard's card exports.

Rules to know#

  • Editing, cancelling, vendor invoice details, missing item masters and Request Material are in Manage GRNs.

  • A GRN line whose item has no complete Item Master or unit conversion is still saved, but the item is flagged as incomplete. On the saved GRN, the creator can use Notify Purchase Members, and the notified members fix the line with Add to Item Master or Update Item Master; see Items without a complete item master. Items can also be completed from Item Master → Incomplete Items: see Complete incomplete items and Add a missing item from a goods receipt.

  • A saved GRN line whose item has lot tracking switched on shows Create Lot, which opens a new spirit lot in Spirit Maturation for that line. The lot form takes the Invoice Number and Invoice Date from the GRN (you can change them). A lot needs the line's inventory batch, so add the line to inventory (Add To Inventory) before creating its lot. Once the lot exists the button is greyed out with Lot already created for this item. See Spirit lots.

Next step · QualityInspect the goods →If no line needs inspection, go straight to Add to inventory.

Common errors#