Example. A requester asked for 100 bolts, but the approver rejected the request: the size was wrong. The requester opens it, clicks Edit, corrects the item and saves; the approvers are told and approval starts again. A month later a second batch is needed, so they open the old request and click Duplicate PR to start from a copy.

Raising, approving, cancelling and closing lines from stock are in Raise a purchase request and Approve the purchase request. This page covers everything else you do with a request.

Which action to use#

You want toUsePossible when
Correct a request nothing has been done with yetEditNot cancelled, closed, amended, or approved (when approval is required)
Change a request after some lines are on an RFQ or orderAmend PRYou created it; not cancelled or already amended; approved (when approval is required); not all its orders fully delivered
Start a new request from an old oneDuplicate PRNot cancelled
Enter vendor prices on a request raised from an inquiryUpdate Price RequestRequest Type Inquiry, you are its purchase person
Find or report on requestsList filters and ExportAlways

The buttons are at the top right of the request (Purchase → Purchase Requests → request); filters and Export are on the list. Hover over a greyed-out button to see why it is unavailable.

Edit a purchase request#

Before you start#

✅ Before you start

0/2 ready

Steps#

  1. Open the edit page

    📍 Purchase request → Edit

    Update Purchase Request opens with the saved details.

  2. Make your changes

    You can change the Date, Expected Delivery Date, Department, Purchase Incharge, the work order fields (not on a request raised by a work order, and only until a line is processed), Specify Reason, remarks and the lines that haven't been processed. Request Type can't be changed. Processed lines are highlighted (legend Processed Item Cannot Be Edited). The Approvers list can't be changed after the request is created.

  3. Save

    📍 Update

    Click Update. It is enabled once you have changed something. When request approval is switched on, a notice Approvers Will Be Notified explains that saving sends the request back for approval. Click Understood, Proceed. When your company uses Tasks, open tasks for the request are completed and the approvers get new review tasks (in Sequential mode, the first approver).

What happens#

  • The request keeps its number. The change is recorded in the Audit Log, and lines show Added, Modified or Removed on the items table.
  • The request goes back to approval status Pending for a new round, whether it was pending, partially approved or rejected.

Edit is greyed out with "PR once closed cannot be edited. You can amend this PR", "PR has been cancelled and cannot be edited", "PR has been amended and cannot be edited", or when the request is approved and approval is required (use Amend PR).

Amend a purchase request#

Use Amend PR when the request can no longer be edited because some lines are already on an RFQ or purchase order.

Before you start#

✅ Before you start

0/2 ready

Steps#

  1. Open Amend Purchase Request

    📍 Purchase request → Amend PR

    The form opens with the request's details and lines, numbered as an amendment of the original.

  2. Change the request

    Change quantities, add lines or remove unprocessed lines. Processed lines can't be edited, and the work order can't be changed.

  3. Save

    📍 Amend

    Click Amend. It is enabled once you have changed something and the request has at least one line. When request approval is switched on, the amended version goes through approval again.

  4. Update the RFQs, if any

    📍 Amended request → Amend RFQ

    On the amended request, Amend RFQ (shown instead of Create RFQ when the request already has RFQs) opens Choose RFQ for Amendment, listing the open RFQs made from it. Select one and click Proceed to Amend RFQ, or click Create RFQ for the new lines. If there are none, you see No open RFQs found.

What happens#

  • The original request becomes Amended; its purchase orders and RFQs are linked to the new version. The original's open linked task is cancelled.
  • The new version shows This PR has been amended from ….
  • Cancelling the amended version lets you use the original again.

Amend PR is greyed out when the request is cancelled or already amended, or when all its purchase orders are fully delivered ("All related purchase orders are fully delivered. Amendment not allowed.").

Duplicate a purchase request#

  1. Start the copy

    📍 Purchase request → Duplicate PR

    Duplicate Purchase Request opens dated today, with the original's Department, Purchase Incharge, Request Type, Specify Reason and remarks, no work order and no lines.

  2. Pick the lines

    📍 Choose Items

    Click Choose Items, tick the original's lines you need and click Confirm. Change quantities as needed.

  3. Save

    📍 Create

    Click Create. It is a new request with its own number and its own approval round; the original isn't changed.

Duplicate PR is greyed out without Purchase Requests: Create ("You don't have permission to create Purchase Requests.") and for a cancelled request ("Cancelled Purchase Requests cannot be duplicated.").

Enter vendor prices on an inquiry request#

When sales asks for vendor prices from an inquiry (Inquiry → Request Vendor Pricing), a purchase request with Request Type Inquiry is raised for the chosen purchase member. Prices can come back two ways: through an RFQ (see RFQ to purchase order), or directly here.

  1. Open Update Vendor Price Request

    📍 Purchase request → Update Price Request

    The button is shown only on Inquiry requests, and only to the purchase person the request is assigned to.

  2. Enter the prices

    For each line enter or check the Quantity, UOM and Unit Price; Amount is calculated. Upload vendor quotes on the line if needed.

  3. Save

    📍 Update

    Click Update. Quantity, UOM and Unit Price are required on every line ("Please fill all required fields (Quantity, UOM, Unit Price) before updating.").

The prices are shown on the inquiry's Vendor Price Request tab to the inquiry's costing members (the tab appears when Costing and Purchase are switched on). Update Price Request is greyed out when the request is cancelled, closed or already amended, when all its items are closed, or when your role lacks Purchase Requests: Update.

Find, filter and export requests#

Filters and list tags#

Purchase → Purchase Requests can be filtered by Date, Status, Approval Status (Pending, Approved, Rejected, Partially Approved; shown when request approval is switched on), Requested By, Purchase In Charge, Department and Request Type (Stock, Outsourcing, Customer Order, Inquiry, Others). The Unprocessed Items column shows how many lines are still unprocessed (N Item(s) Unprocessed), or Cancelled, Amended, All Items Processed or No Items. The Work Orders link on a row lists the linked work orders with their date and customer. Create RFQ and Amend RFQ are on the request itself, not on the list.

Export#

Click Export on the list. The Excel file has one row per line of the filtered requests: Request Date, PR No., Item Description, Quantity, PO No., RFQ No., Purchase Incharge and Requested By. Cancelled and amended requests aren't exported. Export is greyed out when the list is empty or your role lacks Purchase Requests: Export. If no request matches the filters at your current Location, or the export fails, an Error message appears and no usable file is produced.

Remarks after saving#

On a saved request, Add Remarks under Purchase Request Remarks opens the remarks for editing: click Add, type the remark and click Save. Each remark is dated and shows who added it.

Common errors#